So I've had an order of operations for the project in my head for a while, but I'm fairly confident that I've firmed it up now and wanted to share it with you.
1. Strip doors and door frames - Done!
2. Start to get moldings replicated - In progress
3. Remove wall between living room and kitchen - by Nov. 2007
4. Install new outlets in bathroom & kitchen and add recessed lighting to most rooms - Nov. 2007
5. Remove plaster in lath in closets and foyer, replace with drywall - Dec. 2007
6. Refinish closet floors and add custom closets - Jan 2008
7. Remove all bedroom plaster and lath, replace with drywall - March 2008
8. Sand doors and repaint - March 2008
9. Remove all plaster and lath in living room and kitchen, replace with drywall - August 2008
10. Redo Kitchen - Start August 2008, complete Feb. 2009
11. Redo Bathroom - April 2009.
Now that I've looked at the list, it's a big project, but it should be well worth it. Thoughts? Send them my way.