With the clock ticking before my work permit runs out, I've got to keep things moving forward and get the majority of the work done before mid-March. Now that I have the experience, I've established a project schedule to help me move things forward and track progress.
Lots of detail work will have to be completed after all this work, but this covers the bulk of stuff that needs to be done.
Feast upon the latest edition!
Oct. 19th - Demolition, particularly moldings and removal of upper kitchen cabinets.
Oct. 25th - 26th - Remainder of Demolition, including kitchen wood floor.
Nov. 1st - 2nd - Dumpster weekend (will likely need to take a Friday off) if deemed necessary. Begin to put on furring strips and level ceiling. POSSIBLY IN LOS ANGELES!
Nov. 8th - 9th - Run cable, intercom and loudspeaker wire, begin to insulate, get plumbing estimates, begin electrical.
Nov. 15th - 16th - IN MIAMI
Nov. 22nd - 23rd - Finish electrical and insulation, frame out kitchen wall, begin ceiling drywall.
Nov. 29th - 30th - Insulate and drywall.
Dec. 6th - 7th - Mud & Tape
Dec. 13th - 14th - Mud & Tape
Dec. 20th - 21st - Sand & Prime
Dec. 27th - 28th - Install wood flooring and refinish floors
Jan. 3rd - 4th - Install kitchen cabinets/counter tops
Jan. 10th - 11th - Install kitchen cabinets/counter tops
Jan. 17th - 18th - Grace week
Jan. 24th - 25th - Grace week
Jan. 31st - Feb. 1st - Begin Bathroom demolition
Feb 7th - 8th - Plumbing work
Feb. 14th - 15th Insulate/drywall/re glaze tub
Feb. 21st - 22nd - ASPEN SKI TRIP!
Feb. 28th - March 1st - Tile Work